As you might have noticed, the Harvey Street Improvements are still happening! You’ll find the latest update from the City below. For further details, consult the official project website and/or join the email distribution list by emailing Esme Schornstein at milwaukiesafe@milwaukieoregon.gov.
What’s Happening Now?
Crews continue to install and reconnect water service lines on Harvey Street between 32nd Avenue and 36th Avenue. Residents will receive a 48-hour notice before any temporary water shut-off affects their homes.
Week of May 25:
Harvey Street between 32nd Avenue and 36th Avenue:
- Crews will do water service line installations and connect them to existing water meters serving nearby homes.
Harvey Street and 33rd Avenue:
- Crews will install a new water service line and connect it to existing water meters serving nearby homes.
Week of June 1:
Harvey Street and 33rd Avenue:
- Crews will continue to install a new water mainline and service lines and connect them to existing water meters serving nearby homes.
- Crews will install new fire hydrants.
Week of June 8:
Harvey Street and 33rd Avenue:
- Crews will continue installing new water service lines and fire hydrants.