Harvey Street Improvements Update (Late May / Early June)

As you might have noticed, the Harvey Street Improvements are still happening! You’ll find the latest update from the City below. For further details, consult the official project website and/or join the email distribution list by emailing Esme Schornstein at milwaukiesafe@milwaukieoregon.gov.

What’s Happening Now?

Crews continue to install and reconnect water service lines on Harvey Street between 32nd Avenue and 36th Avenue. Residents will receive a 48-hour notice before any temporary water shut-off affects their homes.

Week of May 25:

Harvey Street between 32nd Avenue and 36th Avenue:

  • Crews will do water service line installations and connect them to existing water meters serving nearby homes.

Harvey Street and 33rd Avenue:

  • Crews will install a new water service line and connect it to existing water meters serving nearby homes.

Week of June 1:

Harvey Street and 33rd Avenue:

  • Crews will continue to install a new water mainline and service lines and connect them to existing water meters serving nearby homes.
  • Crews will install new fire hydrants.

Week of June 8:

Harvey Street and 33rd Avenue:

  • Crews will continue installing new water service lines and fire hydrants.